Explain any constraints in using the top-down versus bottom-up approach in duration estimating.

What will be an ideal response?


The first part of this answer should show the contrast between top-down and bottom-up and the
accuracy of information as a function of the source. The next part of this answer should reflect
the influence of management in developing duration estimating (top-down) and the constraints
that can impose.

Computer Science & Information Technology

You might also like to view...

Fill Color (as it applies to Excel)

A) is the background color of a cell. B) is black by default. C) is not adjustable. D) is handled automatically depending upon the contents of the cell.

Computer Science & Information Technology

The selection structure where the logic can flow only to one of the two alternatives, never to both is called a(n) ____ structure.

A. if-then B. if-then-else C. loop D. while

Computer Science & Information Technology

A company hires a third-party firm to conduct an assessment of vulnerabilities exposed to the Internet. The firm informs the company that an exploit exists for anFTP server that had a version installed from eight years ago. The company has decided to keep the system online anyway, as no upgrade exists form the vendor.Which of the following BEST describes the reason why the vulnerability exists?

A. Default configuration B. End-of-life system C. Weak cipher suite D. Zero-day threats

Computer Science & Information Technology

Manually created DB Snapshots are deleted after the DB Instance is deleted.

a. true b. false

Computer Science & Information Technology