If an assembly line has a target takt time of 10 minutes per unit (due to capacity constraints), how many units per day can be produced? Assume that a production day is 480 minutes.

a. 10 units
b. 48 units
c. 400 units
d. Cannot be determined from the information given


b. 48 units

Business

You might also like to view...

If a selection test is not ______, it cannot be valid.

A. personal B. critical C. negligent D. reliable

Business

How do primary data differ from secondary data?

What will be an ideal response?

Business

Which industry has been relying on neural network technology for over two decades?

A. Finance B. Hotels C. Food service D. Healthcare

Business

Which of the following is correct with regard to a holder in due course?

A) A holder in due course must notify subsequent transferees of his holder in due course status. B) A holder in due course can give greater rights to a transferee than he has as a holder in due course. C) A holder in due course can obtain greater rights to payment of an instrument than his transferor had. D) A holder in due course is primarily liable on an instrument.

Business