Assume that activity G has the following times:
Early start time = 7 days
Early finish time = 13 days
Late start time = 15 days
Late finish time = 21 days
Which of the following statements is TRUE about activity G?
A) Activity G takes 14 days to complete.
B) Activity G has a slack time of 8 days.
C) Activity G is on the critical path.
D) Activity G takes 2 days to complete.
B
You might also like to view...
The planning/control cycle has two planning steps. They are
A. (1) research planning, then (2) receive feedback. B. (1) make the plan, then (2) set it aside for a period of time. C. (1) make the plan, then (2) carry out the plan. D. (1) review previous plans, then (2) evaluate plans. E. (1) research planning, then(2) look for ways to cut costs.
In order for the brand to remain healthy, the least value of the consumer franchise-building percent ratio should be:
A) 20 percent. B) 40 percent. C) 50 percent. D) 70 percent.
If an offer does not specify a time for acceptance, the offer terminates at the end of a reasonable time
Indicate whether the statement is true or false
According to Modigliani and Miller's second paper, firms should use ________% debt to maximize the value of the firm
A) 100 B) 20 C) 40 D) 80 E) 60