A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities B, C, and D can be represented by a hammock activity
What are the early start and late finish times associated with this hammock activity?
Time Predecessor
A 7
B 8 A
C 13 B
D 8 C
E 7 A
F 6 E
G 6 A
H 11 G
I 12 H
J 14 D, F, I
A) 11, 30
B) 7, 24
C) 11, 24
D) 7, 36
D
You might also like to view...
Ananda, over her objections, was required by her boss to do something that was significantly against her own values and societal norms. Her supervisor violated Ananda’s ______.
A. right of freedom of speech B. right of equal opportunity C. right to privacy D. right of freedom of conscience
When a manufacturer buys a chain of retail stores that carry its products, it is an example of backward integration.
Answer the following statement true (T) or false (F)
The mechanism that filters large amounts of information about many consumers' previous purchases that may be related in some way in order to predict consumer preferences is known as
A. business-customer marketing. B. specialized marketing. C. client marketing. D. collaborative filtering. E. geofencing.
Under the Registry system Peter and Marisa are neighbours. The only access to Marisa's property is through a lane running along the full length of Peter's property
Marisa has been using this lane to enter her property before Peter became the owner of the property. Which of the following is TRUE? A) Marisa is a tenant at will. B) Marisa has been given a licence by Peter to enter on his land C) Marisa has acquired possessory rights over Peter's land D) Peter's land is subject to a restrictive covenant in favour of Marisa E) Marisa has an easement over Peter's property