A chiller field control circuit ____.
A. is often called an interlock system
B. is a circuit that starts the control procedure before the compressor starts
C. ensures that the appropriate fans and pumps are started in the proper sequence
D. all of the above
Answer: D
You might also like to view...
The points a, b, c, d, and e on the 60 percent component B line, give some temperatures through which a slowly cooled alloy containing 60 percent B, will pass on freezing from a liquid to a solid. Identify the phase or phases, and the amount of each that should exist in the microstructure at each indicated point.
Determine the area of a rectangle 18.0 inches long and 5.60 inches wide rounded to 3 significant digits.
Fill in the blank(s) with the appropriate word(s).
Ceilings/roofs, walls, foundation, all HVAC ducts outside conditioned spaces are ________
A) Areas where vapor retarders are required by the IRC B) Areas which require a Grade 2 Insulation Installation C) Areas in which the IECC requires air sealing and insulation during construction D) Areas which require placement of an energy recovery ventilator
When parts are replaced, corrosion protection coatings must be applied to prevent the new parts from rusting.
Answer the following statement true (T) or false (F)