On November 5, 2014, Commercial Builders, Inc, contracted with Concord to construct a steel building that would house a motorcross track. This contract called for Concord to begin construction ASAP, and Concord began construction. At the time the construction began, Concord had not yet closed on buying the property, but had been given the go-ahead by the owner for construction to begin. The real
estate sale ran into difficulties and did not close. At that time, the building was 85% complete. On January 4, 2015, Concord filed a mechanic's lien against the property. In September 2015, the partially constructed building was completely destroyed by a tornado. Commercial sought to foreclose its lien on the land. The owner said he did not give his consent for the work or a lien. Which of the following is correct?
A) Commercial builders cannot file a lien on the property because Concord did not own the property?
B) Commercial builders cannot file a lien because there is no work to show for the costs
C) Commercial builders cannot file a lien for steel buildings
D) Commercial builders can file a lien because the consent of the owner was implied through the contract and the agreement for the building to begin
D
You might also like to view...
Identify and give an example of three out of the six contradictions that an effective project manager must face.
Fill in the blank(s) with the appropriate word(s).
How does a retailer cooperative function?
What will be an ideal response?
When everyone is pursuing self-direction, the greater good is ultimately served because people learn to accommodate each other in their own long-term interest is an example of the __________ approach.
A. utilitarianĀ B. individualismĀ C. moral-rights D. justiceĀ E. practical
The first U.S. labor unions were organized by
A. Industry, with a focus on local employment issues. B. Industry, with a focus on national employment issues. C. Craft lines, with a focus on local employment issues. D. Craft lines, with a focus on national employment issues.