In each diary kept by the owner/engineer's or contractor's personnel, entries should be made:
A. to document every working day, whether any work is performed or not, or even if you did not go to the project site that day.
B. only if something of particular importance is happening.
C. regularly each time that you visit a site where work is being done; however, no entry need be made unless you were personally at the site and witnessed work being performed.
D. A diary is neither necessary nor desirable on construction.
A
You might also like to view...
If the second character of an OBD II code is a 1 the code is ____________________.
Fill in the blank(s) with the appropriate word(s).
An example of a non-monetary award recognizing hard work is _____.
a. a salary increase b. a company jacket c. a holiday bonus d. paid time off
The average cost of sales when considering the labor cost in a service shop would be best described as ________.
A) The average labor cost for all repairs performed in the shop B) The average cost of the technician's hourly rate and parts cost C) The average labor cost of the Flat rate paid Technicians D) The average labor cost of the hourly paid Technicians
____________________ welding is used in the auto, electronics, pipeline, shipbuilding, aerospace, and high-speed welded tubing industries.
Fill in the blank(s) with the appropriate word(s).