A manufacturer embarking on a Six Sigma program sets the goal of having true Six Sigma capability for all processes by the end of the month
If their current process capability index on a key metric is less than 2.0 and the process capability ratio is 1.0, what must happen with the process standard deviation?
A) The process standard deviation must be doubled.
B) The process standard deviation must be reduced by a factor of six.
C) The process standard deviation must be cut in half.
D) The process tolerances should be doubled.
C
You might also like to view...
Each of the adjustments on the work sheet must be journalized
Indicate whether the statement is true or false
Use the information in Scenario 9.11. If the firm decides to increase its cycle-service level to 90%, what is the new reorder point if all other parameters remain the same for this product?
A) greater than 550,000 units B) greater than 400,000 units but less than or equal to 550,000 units C) greater than 250,000 units but less than or equal to 400,000 units D) greater than 150,000 units but less than or equal to 250,000 units E) greater than 0 but less than or equal to 150,000 units
Anticipatory buying occurs because of an anticipated decrease in interest rates
Indicate whether the statement is true or false
Which of the following is a reason that directly relates to a healthy bottom line?
A. Increased dysfunctional turnover B. Increased employee motivation C. Halo effect in the workforce D. Decreased innovation in strategies