The cost of capital assigned to an individual project should be that rate which:
A) corresponds to the risk level of the firm's division which has responsibility for the project.
B) corresponds to the source of the funds used for the project.
C) corresponds to the latest pre-tax cost of debt and equity for the overall firm.
D) is the firm's current weighted average cost of capital.
E) considers both the nature and the characteristics of the actual project.
E
You might also like to view...
The workload approach is used to determine the type of sales force structure required by a company
Indicate whether the statement is true or false
What organizational pattern works best with presentational software that allows nonlinear movement, such as Prezi?
a. spatial b. problem-cause-solution c. topical d. chronological
An exculpatory clause that results from superior bargaining power is usually found to be void
Indicate whether the statement is true or false
A court may, at times, discharge a party who has not performed
Indicate whether the statement is true or false