When completing a forward pass you carry the early finish to the next activity where it becomes its early start, unless the next succeeding activity is a merge activity. In this case you select the largest early finish number of all its immediate predecessor activities. Why do you select the largest early finish number?
What will be an ideal response?
Acknowledging that the finish number represents the activities' early finish, the largest early finish number is selected because all preceding activities must be completed before an activity can begin. If anything less than the largest number is chosen, there will not be enough time for all preceding activities to finish.
You might also like to view...
In addition to defining the problem and developing an approach, qualitative research is also appropriate when facing a situation of uncertainty
Indicate whether the statement is true or false
The time needed to develop a graphic, the cost of developing the graphic, and the effectiveness of the graphic are the only considerations in the use of graphics
Indicate whether the statement is true or false
Bruce Corporation makes four products in a single facility. These products have the following unit product costs: Products ABCDDirect materials$19.90$15.20$20.80$23.20Direct labor 12.20 8.70 10.50 7.40Variable manufacturing overhead 1.60 2.10 2.00 2.10Fixed manufacturing overhead? 10.80? 11.90? 8.80? 10.70Unit product cost$44.50$37.90$42.10$43.40Additional data concerning these products are listed below. Products ABCDGrinding minutes per unit 1.20 0.70 0.60 0.60Selling price per unit$59.30$51.70$59.50$55.60Variable selling cost per unit$3.60$1.50$2.20$3.60Monthly demand in units 4,000 2,000 4,000 2,000The grinding machines are potentially the constraint in the production facility. A total of 9,000 minutes are available per month on these machines.Direct
labor is a variable cost in this company.Up to how much should the company be willing to pay for one additional minute of grinding machine time if the company has made the best use of the existing grinding machine capacity? (Round your intermediate calculations and final answer to 2 decimal places.) A. $0.00 B. $18.33 C. $12.20 D. $19.30
Risk cannot be transferred because ultimately your own project will suffer the consequences if the event occurs
Indicate whether the statement is true or false