A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below. Activity times are in weeks.
Now assume that the times listed are only the expected times instead of being fixed times. Is the probability of being finished in fewer than 25 weeks more or less than 50%?
The probability is less than 50% because 25 weeks is less than the mean time of 27 weeks.
You might also like to view...
Explain the difference between flat and tall organizations.
What will be an ideal response?
If a marketer annoys a connector, the connector would most likely
A) pay more attention to the marketer in the future. B) send the marketer to another, less busy connector. C) demand an exclusive. D) ignore the marketer and furnish negative media coverage. E) embargo the marketer's story.
GM's insistence on sticking to a bureaucratic culture combined with its M-form structure and its subsequent failure to adapt to changing customer preferences for more fuel-efficient cars, produce higher quality, and create innovative designs best exemplifies
A. groupthink. B. decentralization. C. founder imprinting. D. core rigidity.
In The Theory of Moral Sentiments, Adam Smith:
a. Says that not everyone is happy for our success. b. Says that everyone can see situations in the same way. c. That success is best earned gradually. d. Both a and b e. Both b and c f. Both a and c