When considering risk response development, changing the plan to eliminate the risk or condition is known as ________ the risk.
Fill in the blank(s) with the appropriate word(s).
avoiding
Risk avoidance is changing the project plan to eliminate the risk or condition.
You might also like to view...
What is brand equity?
What will be an ideal response?
The offering of services for cash is recorded in the revenue journal
Indicate whether the statement is true or false
"There are many good reasons why you might want to go into business for yourself," said Dr. Peter Parillo to his PhD candidate, Ram Yadav. "But these good reasons do not include
A. watching the market embrace your ideas and products." B. seeking challenge, profit potential, and enormous satisfaction." C. finding conventional paths to economic success closed." D. seeking power and control over others." E. finding one's progress or ideas blocked at big corporations."
Which of the following project audit report questions addresses PMBOK's quality management knowledge area?
A) Are quality metrics developed, measured, and monitored? B) Are minutes of meetings stored and distributed? C) Is the project team being recognized and rewarded? D) Does the project plan consist of a contingency plan?