Three alternatives identified as X, Y, and Z were evaluated by the B/C method. The analyst calculated project B/C values of 0.92, 1.34, and 1.29. The alternatives are listed in the order of increasing equivalent total costs. The analyst is not sure whether an incremental analysis
(a) What do you think? If no incremental analysis is needed, why not; if so, which alternatives
must be compared incrementally?
(b) For what type of projects is incremental analysis never necessary? If X, Y, and Z are all
this type of project, which alternatives should be selected based on the calculated B/C
values?
What will be an ideal response?
(a) Incremental analysis is needed between alternatives Z (challenger) and Y
(b) Incremental analysis is not needed for independent project; select Y and Z
You might also like to view...
?Figure 37-2:
Use Figure 37-2. What wind speed or speeds will produce 750 W of power??
Fill in the blank(s) with the appropriate word(s).
El voltaje de prueba más común de megaóhmetros es de:
a. 25 VCD. b. 60 VCA. c. 500 VCD. d. 10.000 VCA.
What is washed sand?
What will be an ideal response?
? Identify and state the historical significance of Dwight Eisenhower.
What will be an ideal response?