What is PDM? Why is it useful?

What will be an ideal response?


The precedence diagramming method is used to help project managers plan, schedule, monitor, and control their projects. PDM is useful because it provides the expected project completion time; probability of completion at any given period during the project; critical activities that directly affect the completion time; activities that have extra time so that resources can be shifted to critical activities during those activities with extra time; and the start and the end times of all activities.

Business

You might also like to view...

On a bank reconciliation, bank charges for the month are added to the cash balance per the books

a. True b. False Indicate whether the statement is true or false

Business

In order for a wage increase to actually improve the recipient's purchasing power and standard of living, it must

A. be larger than the increase in the CPI. B. be regulated through an escalator clause. C. be a cost of living adjustment. D. be based on merit.

Business

In Kettle Cafe's suit against Food Services, Inc, the court issues a judgment in Kettle's favor. The judgment can be appealed to an appropriate court of appeals by

a. either party. b. Kettle only. c. Food Service only. d. neither party.

Business

Cleaners & Solvents, Inc (CSI), engages in de-ceptive advertising when it markets its product Dirt Remover as able to kill germs over long periods of time. In an action against CSI regarding Dirt Remover, the firm is ordered to stop its false advertising of Dirt Remover and other products. This is

a. a counteradvertising order. b. a multiple product order. c. a "cooling-off" law. d. a validation notice.

Business