Which of the following terms only considers the time it takes for a system to fail while it is operating but does not take into account any downtime associated with the repairs the system may need?

a. reliability
b. availability
c. redundancy
d. maintainability


a. reliability

Business

You might also like to view...

Which of the following would the auditor most likely do when testing the existence assertion for inventory?

a. Observe the client's count of the annual physical inventory and perform test counts. b. Review vendor invoices for the amounts recorded. c. Review open purchase orders at year end. d. Trace raw material purchases to invoices and to the general ledger.

Business

A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $6,000 per week for every week the project extends beyond 25 weeks

What is the lowest total cost duration for completing this project? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $22,000 B A 12 $18,000 9 $32,000 C A 15 $22,000 9 $62,000 D B 3 $9,000 2 $18,000 E C 9 $15,000 5 $35,000 F E 7 $5,000 5 $8,000 G D 8 $13,000 6 $23,000 H A 12 $20,000 8 $32,000 J H 6 $45,000 4 $56,000 A) 34 weeks B) 36 weeks C) 40 weeks D) 43 weeks

Business

Ms. Roehm was successful in her wrongful termination suit against Walmart

Indicate whether the statement is true or false

Business

Valence can be positive, negative, or zero.

Answer the following statement true (T) or false (F)

Business