If the most optimistic and pessimistic times for a task are 3 and 11 days, respectively, then the variance for the duration of the activity ______.
A. = (3 – 11)/6) raised to 2
B. = (11 – 3)/6) raised to 2
C. = (11 – 3)/3) raised to 2
D. = (3 – 11)/3) raised to 2
B. = (11 – 3)/6) raised to 2
You might also like to view...
________ represent values of a variable that are unknown, either because respondents provided ambiguous answers or their answers were not properly recorded
A) Missing responses B) Inconsistent responses C) Out-of-range values D) Invalid responses E) Edits
If dividend projections include the effect of inflation, then the discount rate used should be a ____________________ rate
Fill in the blank(s) with correct word
Corporate strategy asks, ______?
A. which industries should we enter B. what products should we offer C. at what price should we sell these products D. in which markets should we advertise
Discuss the accounts receivable turnover ratio