All of the following are true about as-built drawings except _____.
a. they are submitted to the architect/engineer as part of the closeout documents.
b. the general contractor is responsible for recording changes.
c. they are provided to the local building inspector to certify all local codes are met.
d. they are developed to demonstrate project changes as they occur on site.
c. they are provided to the local building inspector to certify all local codes are met.
You might also like to view...
The first Roman emperor to convert to Christianity was
a. Licinius. b. Diocletian. c. Valerian. d. Constantine.
The process of incorporating an information signal onto a carrier wave is called ________
Fill in the blank(s) with correct word
When estimating a job, a contractor allows $6,400 for placing 125 cubic yards of concrete. How much is allowed for each cubic yard of concrete (Round to two decimal places)?
What will be an ideal response?
For the refrigeration system to operate correctly, the condenser must always be at a lower saturation temperature than the evaporator.
Answer the following statement true (T) or false (F)