What are the five choices an owner has if the lowest bona fide bid or negotiated price exceeds the budget of the project?
What will be an ideal response?
The five options are (1) approve an increase in the fixed limit, (2) authorize
rebidding or renegotiating, (3) terminate and pay for work performed and
termination expenses if the project is abandoned, (4) cooperate in project
revision to reduce cost, and (5) implement any other mutually acceptable
alternative.
You might also like to view...
Explain the zero tolerance at MMC method.
What will be an ideal response?
The requirements for grounding and bonding electric services can be found in _____.
a. NEC Article 225 b. NEC Article 230 c. NEC Article 240 d. NEC Article 250
According to 70E Section 110.2(C), training of employees in emergency response includes _____.
a. equipment inspection b. selection of PPE and insulated tools c. use of fire extinguishers d. methods of first aid
When applied to systems with air cooled condensers, what is the lowest outside ambient temperature that balanced-port valves can typically work without head pressure control?
A) 25°F B) 35°F C) 45°F D) 15°F