How does the progress payment system work in the construction industry?

What will be an ideal response?


In the progress payment system the contractor is paid incrementally
commensurate with the percentage of work completed. The common law’s
“work first and then be paid” rule is divided into units of the work: as each
unit is completed, payment is due for that work. The units can be either
stages of completion or time elapsed.

Trades & Technology

You might also like to view...

What are the three primary things a court judgment seeks to do for compensatory damages?

What will be an ideal response?

Trades & Technology

The water content in a soil is known to be .2 m3/m3 and the potential of pure water outside the system is assumed to be 0. If the soil is a clay loam you would calculate the soil water potential (in kPa) to be

A) 20 B) -3100 C) -5 D) 0 E) -20

Trades & Technology

The policymakers' challenge involves matching the risk associated with the food safety concern to the acceptable policy option

Indicate whether the statement is true or false

Trades & Technology

In _____ each animal can be traced back to only one common ancestor.

Fill in the blank(s) with the appropriate word(s).

Trades & Technology