Discuss why it is important the project manager understand the project scope and how that applies to developing the project schedule.
What will be an ideal response?
It’s important this answer show the student understands what information is in
the charter and that it represents the initial intent of the customer with regards to
the deliverable and proposed delivery schedule.
You might also like to view...
Answer, and explain: For large lists, deleting an item from a linked list compared to deletion from an array is
a. more efficient. b. less efficient. c. about the same. d. depends on the size of the two lists.
Which of the following methods sets the mnemonic of a menu item?
a) setFont b) setMnemonic c) setMenuMnemonic d) setText
A ____ is the structure that repeats actions while some condition continues.
A. decision B. loop C. branch D. block
What are the steps to crop an image?
What will be an ideal response?