The____ method is the most sophisticated preliminary estimating technique and provides the greatest ability to manage the cost of projects from conception to construction.
A. assembly
B. piece
C. elemental
D. labor
Answer: C
You might also like to view...
When diagnosing the cause of no engine braking during Manual Low operation: Technician A checks for a defective oil pump. Technician B suspects a damaged drive link. Who is correct?
A. A only C. Both A and B B. B only D. Neither A nor B
A mass of 0.025 kg of steam at a quality of 10 percent and a pressure of 200 kPa is heated in a rigid container until the temperature reaches 300°C. The pressure at state 2 is nearest:
A) 2.25 MPa B) 2.5 MPa C) 2.75 MPa D) 3.0 MPa
What advantages are there to adding humidity to heated air?
What will be an ideal response?
The basic air conditioning system is made up of which four components?
A. compressor, condenser, evaporator, receiver B. compressor, accumulator, evaporator, metering device C. compressor, condenser, evaporator, metering device D. condenser, evaporator, metering device, filter drier