In a safety stock problem where both demand and lead time are variable, demand averages 150 units per day with a daily standard deviation of 16, and lead time averages 5 days with a standard deviation of 1 day

What is the standard deviation of demand during lead time?
A) 15 units
B) 100 units
C) 154 units
D) 500 units
E) 13,125 units


C

Business

You might also like to view...

In the Atkinson model of project success, a project's impact to the surrounding community would be classified as:

A) An element of the iron triangle. B) A stakeholder benefit. C) An organizational benefit. D) A strategic goal.

Business

In constructing the railroads in the United States, thousands of landowners granted the federal government easements for the placement of railroad tracks. As rail travel declined, many of the routes were no longer used. Many of the railroad tracks were dismantled formally by cities and towns and many were dismantled informally by those seeking to utilize the iron from the tracks and the wooden

ties. In some cases, the tracks were turned into bicycle paths that have served recreational and commuter needs. ?What effect does the removal of the tracks have? A) None, unless the railroad company did the removal B) None, unless the federal government did the removal C) It results in abandonment of the easement D) None, unless the railroad transfers its easement rights back

Business

____________________ is the difference between the net sales and the cost of goods sold

Fill in the blank(s) with correct word

Business

Which is the decimal equivalent of 7%?

A) 0.007 B) 0.07 C) 0.7 D) 7.0

Business