What is the difference between the project iteration schedule and the detailed work schedule?
The project iteration schedule is a broad, overview schedule that identifies the iterations and the use cases or functions assigned to each iteration. Generally this schedule is not detailed enough to assign work. The detailed work schedule is a shorter view and more detailed schedule, such as for each iteration, from which work assignments can be made and progress can be measured.
You might also like to view...
Moderators who write their own focus group project reports try to complete them within three to four weeks
Indicate whether the statement is true or false
What do the “born good” and “tabula rasa” approaches to human morality have in common that the other approaches lack?
a. Humans must relearn after birth what they already knew before birth. b. Humans have a “conscience” that is basically good. c. Soul is joined to the body before birth. d. Unethical or immoral behavior must be learned from others after birth.
Benefits can represent, on average, about __________ of the employer's total payroll costs.
A. 28 percent B. 7 percent C. 12 percent D. 66 percent
Whirlwind Financial Corporation sends its executives to a resort in Mexico¾at taxpayers' expense¾to consider using the firm's cash to buy back its stock and thereby prop up the value. Many of its competitors are doing the same thing. One of the best ways to learn about the ethical responsibilities inherent in operating a business is to look at
A. the mistakes made by other companies. B. the benefits of pursuing profit despite the appearance of impropriety. C. the prevalence of a practice among other corporations. D. who is footing the bill for a particular action.