A small manufacturer builds wooden pleasure boats in a craftsman manner by traditional labor-intensive methods. The first boat is estimated to take 650 hours of skilled labor, which cost $40 per hour

They currently have three workers that can work 2,000 hours a year. They assume that there is a 90% learning curve. How many boats can they build in their first year?


The number of hours available for the first year is 6,000 hours. Use the total time factor from the 90 percent column of Table E.3. The total number of hours needed to make eleven units is 650 × 8.689 = 5,648 hours; twelve would require 650 × 9.374 = 6,093 hours. So they can build 11 in the first year.

Business

You might also like to view...

The changes during the first decade of the 21st century were often disruptive and provided new opportunities for social entrepreneurship across the globe. What is this disruption called?

A. perturbation B. disturbance C. global innovation D. creative destruction

Business

In determining the correct number of Kanban containers, which of the following is NOT a relevant consideration?

a. processing time for the container b. waiting time during production c. transportation time to the shipping area d. cost of storage of the finished product

Business

Honeypots are blogs created solely for marketing purposes

Indicate whether the statement is true or false

Business

Which of the following is NOT considered a soft skill for the workplace?

A) conflict resolution B) programming C) communication D) problem solving E) collaborating

Business