What is the difference between a Gantt load chart and a Gantt scheduling chart?
What will be an ideal response?
The Gantt load chart indicates a planned allocation of capacity–the allocation of the capacity of a department or work center to a particular job or order. The Gantt schedule chart is used to monitor jobs in progress. It indicates which jobs are on schedule and which are ahead of or behind schedule.
You might also like to view...
Which of the following is the rate of return, based on discounted cash flows, a company can expect to earn by investing in a capital asset?
A) accounting rate of return B) bank interest rate C) internal rate of return D) return on investment
If the law changes such that the actions called for in an agency arrangement become illegal after
the agency has been carried on legally for some period of time, what is the consequence? A) The agency is not terminated, but the principal and agent will each become liable for his or her own illegal actions. B) The agency is not terminated, but the principal and agent will each become liable for the illegal actions of the other. C) The agency is terminated effective upon the change in law taking effect. D) The agency is terminated retroactively and the parties must each return any consideration received from the other. E) The agency is terminated retroactively and the parties are left where they are.
When a business makes a cash payment, the Cash account is debited
Indicate whether the statement is true or false
Which of the following can create an express warranties?
a. Affirmation of fact or promise b. Description of the goods c. A sample or model d. All of the above e. None of the above