If a project has an expected completion time of 15 weeks with a variance of 4 weeks, the probability that the project will be completed in 18 weeks is ______.
A. less than 34%
B. between 44% and 68%
C. between 69% and 83%
D. more than 93%
D. more than 93%
You might also like to view...
An operational definition is necessary for a construct to be measured empirically
Indicate whether the statement is true or false
Which of the following is not one of the characteristics of mechanistic organizations?
a. Well-defined departments b. Integration achieved by relying on formal meetings c. Clear and efficient reporting relationships d. Integration achieved by exchanging information as needed
Many states impose no limit on the rate of interest that may be charged:
a. on loans to corporations. b. on consumer credit card transactions. c. on any consumer loan. d. All of the above. e. Two of the aboe.
A ________ requires that the original owners of the firm maintain ownership of their stock for at least 180 days following an IPO
A) green-shoe provision B) lock-up agreement C) letter of commitment D) red herring