Define the following terms:

(a) CPM (Critical Path Method)
(b) Gantt chart
(c) PERT (Program Evaluation Review Technique)


(a) CPM (Critical Path Method): Management tool that assumes that activities durations are known with certainty

(b) Gantt chart: A chart with series of blocks that account for activities in a project during an assigned period.

(c) PERT (Program Evaluation Review Technique): Management tool that assumes activity durations are random

Trades & Technology

You might also like to view...

You ignore the inner workings of a system when you create a ____ diagram.

A. conceptual B. fishbone C. readout D. black box

Trades & Technology

The sawing action with a board used to level placed concrete is called

What will be an ideal response?

Trades & Technology

In an electrical circuit, watts are:

A) The ability to make current flow. B) One coulomb of electrons flowing on one second. C) the ability of electricity to do work. D) Opposition to current flow.

Trades & Technology

To calculate the maximum load that should be placed on a transformer, _______________ the derating factor by the kilovolt-ampere capacity of the transformer.??

Fill in the blank(s) with the appropriate word(s).

Trades & Technology