A project consists of four activities with information as shown in the table. What is the overall standard deviation of the project?
Activity Predecessor Length Variance A -- 10 4 B A 12 3 C B 16 5 D C 14 6 A) 24 B) 18 C) 8.41 D) 4.24
PERT is a deterministic analysis tool allowing for precise times of activities within a project
Indicate whether the statement is true or false
Regarding supermarkets, which of the following is FALSE?
A. The average size of a supermarket is 40,000 square feet. B. They introduced self-service to reduce their costs. C. After-tax profits are very good, averaging 10 to 15 percent of sales. D. They got their start as an experiment during the Depression. E. They average about $20 million a year in sales.