What are the primary grounds on which the contractor can typically terminate the contract?
What will be an ideal response?
The contractor can terminate a contract when the owner fails to make payments
to the contractor that have been earned and are due. This is the only universal reason for
which the contractor can terminate the contract. Another reason for termination by the
contractor would include a condition whereby the construction effort is stopped for a
stipulated period of time by a court or other public authority.
You might also like to view...
The main bonding jumper is located at the _____.
a. last outlet in the branch circuit b. service disconnect c. ground rod or other grounding system d. meter enclosure
____________________ is a fee charged for the use of stockyard facilities
Fill in the blank(s) with the appropriate word(s).
Catfish grown in modern operations are far superior to those in the wild
Indicate whether the statement is true or false
How is vapor barrier taken off? How does the estimator determine the number of rolls required?
What will be an ideal response?