A job has 5 days of processing time left to do before completion, and today is the 10th day of the month. If the job is due on the 14th day of the month, what is its critical ratio?

A. 0.8
B. 0.1
C. 2
D. 5
E. 0.5


Answer: A

Business

You might also like to view...

Identify and explain at least four situations where a written contract is either necessary or recommended.

What will be an ideal response?

Business

Which of the following is true? The results of operations of a component of an entity that either has been disposed of or classified as held for sale shall be reported in discontinued operations if: I. The operations and cash flows of the component have been or will be eliminated from the ongoing operations of the entity as a result of the disposal transaction. II. The entity continues to have a

significant continuing involvement in the operations of the component after the disposal transaction. III. The entity outsources the manufacturing operations of a component and sells the manufacturing facility of the component but continues to sell the product formerly manufactured by the facility sold. a. I, II, and III are all true. b. I and II are true, but III is not. c. Only II is true. d. Only I is true.

Business

Which type of person relies on factual information, such as someone’s past experience and track record as a basis for trust?

a. Disposition-based b. Perception-based c. Cognition-based d. Affect-based

Business

Mick has a project consisting of eight activities (listed in the table with durations and precedence requirements) to complete. He assigned his intern Guinness to sketch a network diagram in AOA and Guinness produced the sketch shown below

Discuss any issues with the apprentice's diagram. Activity Activity time Predecessor A 6 B 8 C 5 A D 9 A, B E 12 A F 11 D, E G 6 C, F

Business