Solve the problem.A ceramics workshop makes wreaths, trees, and sleighs for sale at Christmas. A wreath takes 3 hours to prepare, 2 hours to paint, and 8 hours to fire. A tree takes 14 hours to prepare, 3 hours to paint, and 4 hours to fire. A sleigh takes 4 hours to prepare, 13 hours to paint, and 7 hours to fire. If the workshop has 117 hours for prep time, 71 hours for painting, and 101 hours for firing, How many of each can be made?
A. 7 wreaths, 6 trees, 3 sleighs
B. 6 wreaths, 3 trees, 7 sleighs
C. 8 wreaths, 7 trees, 4 sleighs
D. 3 wreaths, 7 trees, 6 sleighs
Answer: A