What are the five elements a contractor must prove to establish construction acceleration?
What will be an ideal response?
To establish construction acceleration, a contractor must prove five
elements: (1) the contractor experienced an excusable delay and is entitled
to an extension, (2) the contractor properly requests a time extension, (3)
the owner denies the time extension, (4) the owner demands completion by
the original completion date, and (5) the contractor incurs reasonable
increased costs caused by its actual acceleration.
You might also like to view...
Many commercial and industrial complexes use a(n) ____________________ to heat water that is supplied to heat transfer devices that condition the air in a structure or zone.
Fill in the blank(s) with the appropriate word(s).
The part that MOST-Likely allows the pressure plate release mechanism to operate as the crankshaft rotates is:
A. shim B. release bearing C. slip plates D. ball joint
Determine the resultant vector in standard position for the following vectors and express the magnitude to 3 significant digits and the angle to the nearest tenth degree. == 29.4 mi at 180°,
= 21.6 mi at 270°
Fill in the blank(s) with the appropriate word(s).
Calibration procedures are performed ____.
A. before new instrument installation B. after extended shutdown C. after repair D. if the product being manufactured does not meet specifications E. any of the above