After the tilt-up wall panels are lifted off the casting bed and brought into their final locations using a crane, they are plumbed vertical and provided with temporary supports. What do the temporary supports consist of?
What will be an ideal response?
The supports consist of steel pipe braces that are anchored to the panels near their top. The bottom of braces is
anchored to the concrete slab-on-ground if that is the first floor of the building. If the first floor of the building is an
elevated slab, the bottom support for braces is provided by specially constructed, heavy concrete pads.
You might also like to view...
The most common error that students make in creating auxiliary views is when transferring ____________________ into the new view.
Fill in the blank(s) with the appropriate word(s).
How does castrating a male animal benefit the agricultural producer?
What will be an ideal response?
Which of the following is a correct statement regarding crew evaluations?
a. They should never come as a surprise to the crew member. b. Formal evaluations should be conducted every three months. c. Comments on performance should be withheld until the formal evaluation. d. Advise the crew members to improve their performance just before the formal evaluation is scheduled.
A(n) ______________________________ is used with the turning radius gauge to measure caster and camber in degrees.
Fill in the blank(s) with the appropriate word(s).