Which documents are not part of the project manual?

a. Contract items
b. Specifications
c. Sequence cost comparison
d. Bidding documents


c. Sequence cost comparison

Trades & Technology

You might also like to view...

When a code 111 is displayed on MD/SM, which of the following should be true?

A. No logged historic codes B. No active codes C. No ECM to J1939 communication D. The ECM should be replaced

Trades & Technology

Bench testing of a starter should be done __________

A) After reassembling an old starter B) Before installing a new starter C) After removing the old starter D) Both A and B

Trades & Technology

Gas fired rooftop units are normally vented though

A) Draft hoods connected directly to the unit B) A separate power venter C) Double wall vent pipe connected to the top of the unit D) Double wall vent pipe connected to the side of the unit

Trades & Technology

In addition to protecting other workers from exposure to electric arcs, welding screens _____

a. prevent drafts from interfering with the stability of the arc b. reduce glare on the workpiece c. mark a confined space d. support workpieces for overhead welding

Trades & Technology