Explain what concurrent delays are and how a contractor could prove that they have occurred on a project

What will be an ideal response?


When more than one event delays a project it is said to have been delayed by concurrent delays (James, 1990). It is difficult to determine which delays are concurrent delays and if the owner and the contractor are not able to determine the affects of concurrent delays legal proceedings might be required to resolve the issue.

Trades & Technology

You might also like to view...

Los sistemas de agua caliente funcionan a alrededor de:

a. 110-150 °F (43,33 - 65,55 °C) b. 160-180 °F (71,11 - 82,22 °C) c. 200-225 °F (93,33 - 107,22 °C) d. temperatura ambiental.

Trades & Technology

Concrete normally attains its design strength in about _____.

a. 14 days b. 21 days c. 28 days d. 30 days

Trades & Technology

Which of these is a popular tool for hand lettering?

a. a compass c. Ames guide® b. a protractor d. a T square

Trades & Technology

The master link uses the same pins and bushings as the rest of the track.

Answer the following statement true (T) or false (F)

Trades & Technology