Suppose you have the following project digraph. (The numbers in parentheses represent hours.)
Consider the following timeline using two processors.

A. This is the timeline one gets using the critical-path algorithm.
B. This is the timeline one gets using the decreasing-time algorithm.
C. This timeline is an illegal schedule.
D. This timeline is an optimal schedule.
E. none of these


Answer: C

Mathematics

You might also like to view...

Provide an appropriate response.Find any local extrema (maxima, minima, or saddle points) of    given that   and  

A. Local minimum at  
B. Local maximum at  
C. Saddle point at  
D. Local maximum at  

Mathematics

Two terms in the Fibonacci sequence are given. Find the specified term.F18 = 2584 and F20 = 6765. Find F19.

A. 5168 B. 13,530 C. 9349 D. 4181

Mathematics

Solve the proportion for the item represented by a letter. ? ? H = __________

Fill in the blank(s) with the appropriate word(s).

Mathematics

Determine whether the graph of the equation is symmetric with respect to the x-axis, the y-axis, and/or the origin.y = x + 1

A. origin B. y-axis C. x-axis D. x-axis, y-axis, origin E. none

Mathematics