Given the following data, which job(s) will be late if the shortest process time sequencing rule is used?
Today is day 100.
Job Process Due
Time Date
A 4 104
B 1 106
C 5 109
A) B and C will be late. B) A and B will be late.
C) A and C will be late. D) All jobs will be on time.
C