Suppose you have the following project digraph. (The numbers in parentheses represent hours.)
Using the priority list F, E, A, D, B, G, C and the priority-list model to schedule this project with two processors, the project finishing time is

A. 22 hours.
B. 18 hours.
C. 21 hours.
D. 17 hours.
E. none of these


Answer: A

Mathematics

You might also like to view...

Graph the function.f(x) = 2log2x

A.

B.

C.

D.

Mathematics

Provide an appropriate response.Use -1 =  to solve .

What will be an ideal response?

Mathematics

From the list below find the expression, identical to the given. ? ?

A.
B. ?
C. ?
D. ?
E. ?

Mathematics

Find the linear equation that meets the stated criteria.The linear equation y = 221x + 6320 provides an approximation of the annual cost (in dollars) to rent an apartment at the Leisure Village Retirement Community, where x = 1 represents 1983, x = 2 represents 1984, and so on. Write an equation that yields the same y-values when the exact year number is entered.

A. y = 221(1983 - x) + 6320 B. y = 221(x - 1983) + 6320 C. y = 221(1982 - x) + 6320 D. y = 221(x - 1982) + 6320

Mathematics