Positive slack indicates the maximum amount of time
a. that the activities on the critical path should be accelerated to complete the project by the required completion time.
b. that each of the activities in the project can be delayed without jeopardizing completion of the project by the required completion time.
c. that the activities with the positive slack should be accelerated to complete the project by the required completion time.
d. that the activities on a particular path can be delayed without jeopardizing completion of the project by the required completion time.
d
You might also like to view...
_____ is a structured, disciplined approach that facilitates the adoption of new or modified systems by various groups and individuals within an organization.
A. Prototyping B. Data mining C. Change management D. Knowledge extraction
Habits are considered ______.
A. intense life experiences B. unpleasant aspects of the self C. voluntary routines or practices D. inner life, meaningful work, community
When using the allowance method of accounting for uncollectible accounts, the entry to record the estimated bad debts expense is a debit to Bad Debts Expense and a credit to Allowance for Doubtful Accounts.
Answer the following statement true (T) or false (F)
Which article in the U.S. Constitution contains the Necessary and Proper Clause, which provides that Congress may enact all laws necessary and proper to carry out Congress's other enumerated powers?
a. Article I b. Article II c. Article III d. Article IV