Carolina Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under some conditions choosing projects on the basis of the IRR will cause $0.00 value to be lost.
r:  7.75%    Year0
1
2
3
4
CFS ?$1,050
$675
$650
  CFL ?$1,050
$360
$360
$360
$360

A. $11.45
B. $12.72
C. $14.63
D. $16.82
E. $19.35


Answer: B

Business

You might also like to view...

In countries like India and Vietnam, and other emerging markets, amenities such as refrigerators, flush toilets, and cell phones are considered status symbols

Indicate whether the statement is true or false

Business

A standard costing system

a. is not typically used by management for cost planning and cost control purposes. b. is a system in which all costs affecting the three inventory accounts and the Cost of Goods Sold account are stated in terms of actual costs incurred. c. depends on actual costs rather than planned costs. d. is employed with an existing job order costing or process costing system and is not a full cost accounting system in itself.

Business

How do companies such as the Home Shopping Network effectively utilize media-sharing sites? Provide examples, including reference to which two of the 4E frameworks are most active.

What will be an ideal response?

Business

Lots that are expected to be received in a particular period are ______.

A. planned order receipts B. scheduled receipts C. planned lot receipts D. planned inventory receipts

Business