What is the probability of completing the project within 20 days?

Joe used a project management software package and has determined the following results for a given project:

Expected completion time of the project = 22 days
Variance of project completion time = 2.77

A) 0.3849
B) 0.8849
C) 0.1151
D) 0.7642


Answer: C

Business

You might also like to view...

Amortization is the allocation process of writing off bond premiums and discounts to interest expense over the life of the bond issue

Indicate whether the statement is true or false

Business

Within the business plan, the description of venture section details how the product(s) will be manufactured. 

Answer the following statement true (T) or false (F)

Business

On January 1, a company issues bonds dated January 1 with a par value of $730,000. The bonds mature in 3 years. The contract rate is 10%, and interest is paid semiannually on June 30 and December 31. The bonds are sold for $718,000. The journal entry to record the first interest payment using straight-line amortization is:

A. Debit Interest Expense $34,500; debit Discount on Bonds Payable $2000; credit Cash $36,500. B. Debit Interest Payable $36,500; credit Cash $36,500. C. Debit Interest Expense $36,500; credit Cash $36,500. D. Debit Interest Expense $38,500; credit Discount on Bonds Payable $2000; credit Cash $36,500. E. Debit Interest Expense $36,500; credit Premium on Bonds Payable $2000; credit Cash $34,500.

Business

Sketch and discuss the product-process matrix for manufacturing

What will be an ideal response?

Business