A project consists of five tasks. The lengths of the tasks (in hours) are 5, 4, 4, 3, and 3. The tasks are all independent (i.e., there are no precedence relations).Using the critical-path algorithm to schedule the project with two processors, the finishing time is
A. 12 hours.
B. 10 hours.
C. 11 hours.
D. 9 hours.
E. none of these
Answer: C
Mathematics
You might also like to view...
Choose the most reasonable measurement.Tyrell read the nutrition label on the back of his frozen dinner. Choose the most reasonable estimate for the amount of sodium in the dinner.
A. 510 t B. 510 mg C. 510 kg D. 510 g
Mathematics
Solve the system. x + y + z = 1 x - y + 4z = -42x + y + z = -3
A. (1, -4, 4) B. (-4, 4, 1) C. (1, 4, -4) D. No solution
Mathematics
Graph the function y = g(x), given the graph of y = f(x). g(x) = - f(x)
A.
B.
C.
D.
Mathematics
State the domain and range of the given function.f(x) = x2 + 4
A. Domain: (-?, ?) Range: (-?, 4] B. Domain: (-?, ?) Range: (-?, ?) C. Domain: [4, ?) Range: (-?, ?) D. Domain: (-?, ?) Range: [4, ?)
Mathematics