How are noncompensable excusable delays addressed when they occur on projects?
What will be an ideal response?
Non-compensable excusable delays are delays that are not caused by either the owner or the contractor. They are caused by acts of God, or other unforeseeable causes, that are beyond the control of both parties. Delays that are caused by acts of God entitle contractors to receive time extensions, but not damages for the delay. Contracts usually contain a clause, sometimes referred to as a force majeure clause that lists the causes of delays that are non-compensable excusable delays.
You might also like to view...
What is accomplished by the program known as the operating system?
A) It is used to organize information in a "data base." B) It controls communication between the microprocessor and its various input/output devices. C) It translates high-level programming languages to machine code. D) It is a high-level programming language.
The ____ is a masonry or metal covering that may be placed over the flue for protection from the elements.
A. flue B. chimney hood C. chimney cap D. chimney liner
To check the free play of manual slack adjusters of S-cam brakes, you should park on:
a. Level ground and apply the parking brakes, then apply service brakes. b. Level ground and drain off air pressure before checking the adjustment. c. Level ground, chock the wheels and release the parking brakes.
By what title or rank are the heads of the four major functional components of the Incident Management System known?
A. Director B. Chief C. Manager D. OfficeR