Using Table 7.5, what is the earliest that activity D can be finished?

A) 18 days
B) 8 days
C) 13 days
D) 25 days


A

Business

You might also like to view...

Use this earned schedule table to determine the schedule variance ($) for this project at the end of Month 6

Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 PV ($) $125 $275 $500 $875 $1,485 $2,325 $2,670 EV ($) $50 $120 $255 $420 $715 $865 $0 A) -$1,460 B) -$865 C) $865 D) $2325

Business

Explain the four critical components of the LAMP model.

What will be an ideal response?

Business

A(n) ________ maintains a clear sense of purpose and a firm idea of what is involved in creating the project

A) politician B) ambassador C) cheerleader D) visionary

Business

Meeting highlights provide a summary of what went on during the meeting. _________________________

Answer the following statement true (T) or false (F)

Business