A sub-contractor reports that the approved material is no longer in production. The sub-contractor then brings in data claiming the superiority of a new substitute product. The resident project representative should:
A. approve the changes and carefully file the data.
B. ask the owner if it will be acceptable.
C. leave the decision to the design engineer of record.
D. refer the decision to the Superintendent.
E. refer the matter to the construction manager
C
You might also like to view...
_______ valves use a disc and seat to regulate the flow.
Fill in the blank(s) with the appropriate word(s).
Which of the following does not represent a steel joist series?
A) J-series B) DLH-series C) LH-series D) H-series E) K-series
Which type of variable effort steering design uses a variable bi-directional magnetic rotary actuator built into the steering rack?
A) TFE B) EVO C) SSS D) Magnasteer
In an N-channel depletion MOSFET, a large amount of drain current flows when the gate voltage is equal to ____.
A. negative one B. zero C. one D. infinity