Before starting work on three-phase installations, the electrician must give the power company detailed information as to the connected horsepower load. What information does the power company provide for the electrician?
What will be an ideal response?
The power company will specify the following:
1) the location of the service entrance to the building and the location of the meter
board.
2) the type and size of the meter test cabinet and test block.
3) installation standards.