If the standard deviation is 2.78 and the Z value is 1.65, then ______.

A. the expected date of completion is 34.59 weeks if the due date for project completion is 30 weeks
B. the due date for project completion is 34.59 weeks if the expected date of completion is 30 weeks
C. the due date for project completion is 30 weeks if the expected date of completion is 24.51 weeks
D. the due date for project completion is 24.51 weeks if the expected date of completion is 30 weeks


B. the due date for project completion is 34.59 weeks if the expected date of completion is 30 weeks

Business

You might also like to view...

Deposits made directly by the bank would be

A. added to the company's records. B. deducted from the company's records. C. added to the bank statement balance. D. deducted from the bank statement balance.

Business

Umber Company's bank reconciliation for September is presented below. Prepare the necessary adjusting journal entries based on the reconciliation report.UMBER COMPANYBank ReconciliationSeptember 30Bank statement balance$1,350Book balance of cash?$995Add:?Add:??Deposit in transit1,250Proceeds of note?875Bank error275????$2,875??1,870Deduct:?Deduct:??Outstanding checks1,145NSF check plus processing fee?125??Bank service charge?15Reconciled balance$1,730Reconciled balance?$1,730

What will be an ideal response?

Business

If you are conducting an experiment where the probability of a success is .02 and you are interested in the probability of 4 successes in 15 trials, the correct probability function to use is the

a. standard normal probability density function b. normal probability density function c. Poisson probability function d. binomial probability function

Business

An evaluation of the effectiveness and efficiency of various systems within an organization is called a(n) ________ audit.

A. budget B. human resource C. activity-based D. six sigma E. management

Business