Match the following terms to their meanings:
I. Elapsed duration
II. Tracking
III. Project Summary task bar
IV. Project template
V. Team Planner
A. Recording the actual progress of the project's tasks
B. Schedules a task to 24 hours a day
C. Shows a project's resources and tasks assigned to each resource
D. Displays the total duration of your project
E. A Project file that contains sample project information
B, A, D, E, C