A project has four activities. Activity A has no predecessors and a duration of 1 week. Activity B has Activity A as its predecessor and a duration of 4 weeks. Activity C has Activity A as its predecessor and a duration of 3 weeks. Activity D has activities B and C as its predecessors and a duration of 2 weeks. What is the length of critical path for this project?

a. 4
b. 5
c. 7
d. Cannot be determined from the information given


c. 7

Business

You might also like to view...

In preparing financial statements, accountants should consider all of the following except:

a. The objectives of financial reporting. b. The characteristics that make accounting information useful. c. The most useful way to display the information found on the financial statements. d. The presentation of the value of a company.

Business

Which of the following best describes the purpose of a bill of material class?

A. Shows the raw material usage variance. B. Links finished goods to production. C. Links each raw material item to one or more finished good items. D. Shows the issues of raw material items into work in process.

Business

You engage in metacommunications when you communicate with another person, your perception of how well you two are communicating

Indicate whether the statement is true or false.

Business

As part of logical design, analysts design the various parts of the system to perform the physical operations necessary to facilitate data capture, processing, and information output

Indicate whether the statement is true or false

Business