Which of the following will be used in determining the enforceability of a liquidated damages clause in a contract?

A) The naming of the clause a "liquidated damages clause".
B) A statement by the parties that if the contract is breached a set amount of money will be paid by the party in breach to the innocent party.
C) An acknowledgement in the clause that the damages set out are a realistic estimate of loss.
D) At the time of making the contract the dollar amount is a genuine pre-estimate of the damages that would result from a breach.
E) A statement in the clause that the damages payable are not a penalty.


D

Business

You might also like to view...

Via survey questionnaires, you collected data about the trainees’ self-assessment on their behavioral changes from three different times in different places: ? In the classroom immediately after they completed the program ? In the workplace 2 weeks after they completed the program ? In the workplace 2 months after they completed the program Is the above method a reasonable triangulation method?

a. Yes, it is a reasonable triangulation method. b. No, it is not a reasonable triangulation method.

Business

The greatest project risk occurs when:

A) The probability of the event is high and the consequences of the event are high. B) The probability of the event is high and the consequences of the event are low. C) The probability of the event is low and the consequences of the event are high. D) The probability of the event is low and the consequences of the event are low.

Business

Erin is a shareholder in First Aides, Inc, a home healthcare company. As a shareholder, Erin

a. owns shares of stock in First Aides. b. cannot be sued by First Aides. c. cannot sue First Aides. d. is liable for all the debts of First Aides.

Business

Most project management software represents a project in AON format

Indicate whether the statement is true or false.

Business